|
![]() FLSmidth - eHighlights - May 2010
| ||||
| May 2010 |
| ||||
|
Corporate New contracts Product news Projects in progress Services
| Making history at Ste. Genevieve
Construction of the state-of-the-art greenfield project in Ste. Genevieve County, Missouri, was completed in July 2009. And within its first three months of accumulated operation, the massive plant was breaking world records. On 21 November 2009, Ste. Genevieve’s kiln clinker production reached 13,160 tonnes per day (tpd) – becoming the first single kiln production line to break 13,000 tpd. First-class design and engineering With many different companies involved in the plant design, FLSmidth’s web portal, MyFLS, was essential for distributing design documents between Holcim, its main contractor and the engineering firms engaged by FLSmidth. Site preparation Designing for a river with extreme fluctuations The river’s fluctuations also called for an unconventional conveyor belt design for offloading raw materials used in the process such as coal, petcoke and gypsum. The conveyor is mounted on a floating barge at its feed end while it discharges onto another belt on land. So that loading can be accommodated year round, despite river conditions, the belt is pinned at its head end and allowed to pivot and rotate at the feed end. The project schedule included critical engineering and equipment deliverable milestones that afforded Holcim every opportunity to engage construction contractors as early as possible on this greenfield project. But on-site storage and real estate for preassembly were at a premium, so Holcim took delivery of major components on-site and used off-site locations along the Mississippi River – one in Memphis, Tennessee, and another in Cape Girardeau, Missouri – to assemble fabricated components and equipment, such as process dust collectors, preheater vessels and cyclones. These enormous structures were difficult to transport by road, and in some instances, impossible. But a pier constructed at the harbor’s east bank meant that large equip- ment could be delivered by barge on a just-in-time basis, which was a great asset for logistics planning.
At Ste. Genevieve
FLSmidth supplied core processing equipment, including:
The plant also boasts a range of other equipment from FLSmidth:
Civil and structural design challenges In three areas, the rock was not strong enough to bear the foundations. To overcome this problem, caissons were drilled between the preheater/pre-calciner and cooler structures, between the clinker storage silos and cement mills, as well as in the harbor area. The hybrid preheater design also posed con- siderable layout and design challenges for the structural engineers. The plant’s process design dictated the preheater tower’s vessel layout, which meant that interior columns could not be placed throughout the structure for support. Instead, long-span deep girders were used for supporting all main levels. In addition, because rectangular support framing could not be used in all cases, skewed girders had to be incorp-orated into the design, further complicating the design process. The impressive preheater structure consists of 12 perimeter columns with deep girders spanning between the columns on the seven floors that support major equipment. Steel framing was used to fill in the space between the girders and to construct minor access platforms, while reinforced concrete floor slabs were used on the main floors. After construction workers had erected more than 30,000 tonnes of structural steel, poured more than 58,870 m3 (77,000 CY) of concrete, laid almost 43 km (140,000 LF) of process and utility piping, pulled 1,372 km (4.5 million LF) of cable, moved more than 28,000 tonnes of equipment, and clocked nearly 7 million man-hours, the plant was ready for operation. Commissioning and performance Extensive dry commissioning meant that almost all plant equipment reached full production within the first month after start-up. The operation sequence began when primary crusher came on line in November 2008; two cement mills came online in May 2009, followed by the raw mills in June and first clinker in early July. After two months of accumulated run time, clinker production reached 12,000 tpd. In October, the plant’s availability rating reached an impressive 99.6 percent. Kiln operation was very stable during the start up phase, and the clinker quality met or exceeded Holcim’s requirements. On 21 November 2009, Ste. Genevieve broke its first world record when clinker production reached 13,160 tpd. The first single kiln production line to break the seemingly impossible 13,000 tpd production barrier, this date will be one to remember for FLSmidth, Holcim and Ste. Genevieve. | ||||
|